As 2018 draws to a close, we take a look at the progress of some of our developments in what has been a monumental year for Opendoor Homes.


Adamson Court- Hertford Road, N2

10 affordable homes comprising of 2 and 1 bed flats

Builder:Bugler Developments

Completion due end January 2019


Alexander Road N10

4 affordable 2 bed houses

Builder: Indecon Building Ltd
Completion due May 2019

Window installation in progress. Closing up of the walls and ceilings has commenced. Brick columns to porches has been completed.

Porch roof ready to install


Burgundy House, Edgar Close, Basing Way N3

13 affordable homes comprising of 2 bed flats

Builder: Bugler Developments
Completed on the 21st November 2018


Burnt Oak Registry Office, HA8

30 affordable homes comprising of 1 & 2 bed flats

Builder: Hill Partnerships Ltd
Completion date due June 2020

  • Boundary fences are now fully established.
  • The construction of the concrete frame and delivery of a tower crane will commence in the new year.
  • The piling activity and muck away are due to be completed before or Christmas.


Gordon Court and Pulham Avenue, Elmshurst Crescent, N2

13 affordable homes comprising of 2 bed flats

Builder: Bugler Developments

Completed on the 12th September 2018. Wheelchair flat completed 12th November 2018 and was fully adapted for the resident’s needs.


Hanshaw Drive HA8

6 affordable homes comprising of 2 bed houses

Builder: Indecon Building Ltd

Completion due January 2020

Design work in progress


Norfolk Close N2

8 affordable homes comprising of 1 & 2 bed flats

Builder- Lifebuild Solutions Ltd

Start on site January 2019

 


Prospect Ring N2

50 affordable homes comprising of 1 & 2 bed flats

Builder: Hill Partnerships Ltd

Completion due July 2021.

Design work in progress.

Start on site for demolition due beginning of February 2019


Sheaveshill Court NW9

34 affordable homes. Comprising of 3 bed houses and 2 & 1 bed flats

Builder: Bugler Developments

Completion date due October 2020

Bugler have cleared undergrowth and are due to remove trees. Temporary hoarding off the site has commenced.


West Close Garages EN5

3 affordable 2 bed houses

Builder: Indecon Building Ltd

Completion due July 2019

Substructure blockwork to commence


West Farm Place EN4

4 affordable homes comprising of 2 bed houses and bungalows

Builder: Citiline Construction

Completion due June 2019

  • Cavity insulation taped and neatly installed for the houses
  • Setting out of the substructure brickwork in progress for the bungalows

 


Mount Parade EN4

7 affordable homes comprising of 1 & 2 bed flats

Car park has now been fenced off and ground investigation surveys are being carried out

 


The Croft HA8

33 affordable homes comprising of 1, 2 & 3 bed flats and 2 bed houses

Builder: Bugler Development

Completion due February 2020

Demolition in progress

 


Westbrook Crescent EN4

2 affordable homes comprising of 2 bed houses

Builder: Citiline Construction

Completion due May 2019

Timber dormer window construction complete

 


Salcombe Gardens NW7

6 affordable homes comprising of 2 bed flats

Builder: Rydon Construction Ltd

Completion due July 2019

Scaffolding erected to roof height


Linden Road/ Pine Road N11

6 affordable homes comprising of 2 houses and 4 flats

Builder: Lifebuild Solutions Ltd

Design and enabling works in progress completion due January 2020


Mount Pleasant EN4

12 affordable homes comprising of 2 bed flats

Builder: Kind & Co (Builders Ltd)

Design works in progress. Completion due July 2020