As 2018 draws to a close, we take a look at the progress of some of our developments in what has been a monumental year for Opendoor Homes.
Adamson Court- Hertford Road, N2
10 affordable homes comprising of 2 and 1 bed flats
Builder:Bugler Developments
Completion due end January 2019
Alexander Road N10
4 affordable 2 bed houses
Builder: Indecon Building Ltd
Completion due May 2019
Window installation in progress. Closing up of the walls and ceilings has commenced. Brick columns to porches has been completed.
Porch roof ready to install
Burgundy House, Edgar Close, Basing Way N3
13 affordable homes comprising of 2 bed flats
Builder: Bugler Developments
Completed on the 21st November 2018
Burnt Oak Registry Office, HA8
30 affordable homes comprising of 1 & 2 bed flats
Builder: Hill Partnerships Ltd
Completion date due June 2020
- Boundary fences are now fully established.
- The construction of the concrete frame and delivery of a tower crane will commence in the new year.
- The piling activity and muck away are due to be completed before or Christmas.
Gordon Court and Pulham Avenue, Elmshurst Crescent, N2
13 affordable homes comprising of 2 bed flats
Builder: Bugler Developments
Completed on the 12th September 2018. Wheelchair flat completed 12th November 2018 and was fully adapted for the resident’s needs.
Hanshaw Drive HA8
6 affordable homes comprising of 2 bed houses
Builder: Indecon Building Ltd
Completion due January 2020
Design work in progress
Norfolk Close N2
8 affordable homes comprising of 1 & 2 bed flats
Builder- Lifebuild Solutions Ltd
Start on site January 2019
Prospect Ring N2
50 affordable homes comprising of 1 & 2 bed flats
Builder: Hill Partnerships Ltd
Completion due July 2021.
Design work in progress.
Start on site for demolition due beginning of February 2019
Sheaveshill Court NW9
34 affordable homes. Comprising of 3 bed houses and 2 & 1 bed flats
Builder: Bugler Developments
Completion date due October 2020
Bugler have cleared undergrowth and are due to remove trees. Temporary hoarding off the site has commenced.
West Close Garages EN5
3 affordable 2 bed houses
Builder: Indecon Building Ltd
Completion due July 2019
Substructure blockwork to commence
West Farm Place EN4
4 affordable homes comprising of 2 bed houses and bungalows
Builder: Citiline Construction
Completion due June 2019
- Cavity insulation taped and neatly installed for the houses
- Setting out of the substructure brickwork in progress for the bungalows
Mount Parade EN4
7 affordable homes comprising of 1 & 2 bed flats
Car park has now been fenced off and ground investigation surveys are being carried out
The Croft HA8
33 affordable homes comprising of 1, 2 & 3 bed flats and 2 bed houses
Builder: Bugler Development
Completion due February 2020
Demolition in progress
Westbrook Crescent EN4
2 affordable homes comprising of 2 bed houses
Builder: Citiline Construction
Completion due May 2019
Timber dormer window construction complete
Salcombe Gardens NW7
6 affordable homes comprising of 2 bed flats
Builder: Rydon Construction Ltd
Completion due July 2019
Scaffolding erected to roof height
Linden Road/ Pine Road N11
6 affordable homes comprising of 2 houses and 4 flats
Builder: Lifebuild Solutions Ltd
Design and enabling works in progress completion due January 2020
Mount Pleasant EN4
12 affordable homes comprising of 2 bed flats
Builder: Kind & Co (Builders Ltd)
Design works in progress. Completion due July 2020